gantt
title CCAE Curriculum Implementation Plan
dateFormat YYYY-MM-DD
axisFormat %b %y
section Planning Phase
Initial Planning & Strategy :2024-12-15, 30d
RIAI Policy Alignment :2024-12-20, 45d
Existing Content Assessment :2025-01-05, 30d
section Module Development
Content Reanimation :2025-01-15, 60d
Digital Futures Integration :2025-01-20, 45d
New Specialisation Development :2025-02-01, 45d
section Partnerships
MTU Partnership Integration :2025-01-10, 40d
UCC Collaboration Framework :2025-01-25, 35d
Industry Partner Engagement :2025-02-15, 50d
section Implementation
Staff Development Programme :2025-02-01, 45d
Student Transition Planning :2025-03-01, 30d
Pilot Programme Launch :2025-04-01, 30d
section Milestones
5-Year Innovation Plan Checkpoint :milestone, 2025-01-31, 1d
RIAI Alignment Review :milestone, 2025-02-28, 1d
Partnership Framework Complete :milestone, 2025-03-15, 1d
Programme Ready for Launch :milestone, 2025-04-30, 1d