Project phasing & risk management Gantt Chart

gantt title Project Phasing for Deep Retrofit dateFormat YYYY-MM-DD section Planning Initial Assessment :2024-02-01, 30d Risk Analysis :2024-02-15, 20d Design Development :2024-03-01, 45d section Phase 1 (North-South Block) Site Preparation :2024-06-01, 14d External Works :2024-06-15, 40d M&E Installation :2024-07-01, 30d Commissioning :2024-08-01, 14d section Phase 2 (East-West Block) Site Preparation :2024-06-01, 14d External Works :2024-06-15, 40d M&E Installation :2024-07-01, 30d Commissioning :2024-08-01, 14d